FP Lucas May 2025 construction

F. P. LUCAS BOULEVARD – McKenzie Road to E. Cartwright Road
What
: Existing two-lane asphalt road will be replaced with a new four-lane divided concrete road. The project includes new water and sewer utilities, along with a new multi-use trail and a new bridge section.
When
: Installation of water and sewer utilities are 90% complete, the multi-use trail is 50% complete, and the northbound bridge is 75% complete with new concrete paving. Concrete road construction from McKenzie Road to Cartwright Road will be ongoing through late Spring 2025. The project is expected to be complete in Fall 2025.


South Parkway May 2025 construction 

SOUTH PARKWAY – U.S. 80 to Peachtree Road (Real. Texas. Roads. project*)
What: Reconstruction of new water and sewer utilities and new concrete reconstruction of a two-lane residential street. Sections of the road will be closed during different phases of construction. Residents will have alley access to their homes.
When: Installation of water and sewer utilities are 100% complete and the multi-use trail is 95% complete with full completion in May. The new travel lane concrete paving is 100% complete, with the northern half from Peachtree to U.S. 80 lanes now open to residents and all lanes opening by the end of May. A combination of sodding and hydromulch will be complete in May to restore landscape areas. The project is expected to be fully complete in Summer 2025.


Lorraine RTR May 25 Construction 

VARIOUS STREETS – (Real. Texas. Roads. project*)
What: New water and sewer utility reconstruction and new concrete roads and sidewalks for sections of
 Lorraine Lane, Candise Court, Ivy Drive, Mt. Vernon Drive, Fernwood Drive, Monticello Drive, and the Stoney Glen neighborhood. 
When: Construction started on utilities in late February 2025. Sewer line replacement work on Lorraine Lane is 90% complete, with the Ivy Drive sewer line replacement at 40% complete and will begin waterline replacement after sewer is complete. Paving on Lorraine Lane and Candise Court started in late April and will continue into May. The project will gradually move to the rest of the streets. All road projects are expected to be complete by Spring 2026.

 

For information on all current and future City of Mesquite transportation projects, visit www.cityofmesquite.com/CityConstructionProjects.


*Real. Texas. Roads. is the program name for the road repairs funded by the $125 million bond sale approved by voters in November 2015. Repairs under this program are limited to residential, two-lane roadways. Learn more about 
Real. Texas. Roads.


 The Texas Department of Transportation (TxDOT) manages reconstruction and repair for IH-635, IH-30, IH-20, U.S. 80, and the work on Lawson Road under the Highway Safety Improvement Program grant. For TxDOT updates, visit 
www.drivetexas.org
.