SKYLINE DRIVE – Town East Boulevard to Peachtree Road
What: Four lane divided concrete thoroughfare reconstruction project which will move westbound lanes to the south creating a buffer area that includes a trail, screening wall, and landscaping. The signal at Skyline at Peachtree has been replaced.
When: A project ribbon cutting took place on July 30.
F. P. LUCAS BOULEVARD – McKenzie Road to E. Cartwright Road
What: Existing two-lane asphalt road will be replaced with a four-lane divided concrete thoroughfare. The project includes trails and a new bridge section. Two-way traffic will be maintained on existing or new pavement during construction.
When: City utility improvements are substantially complete. Storm sewer construction is underway for Phase I along with bridge substructure.
EXECUTIVE BOULEVARD and INNOVATIVE WAY
What: Industrial street reconstruction which will include water and sanitary sewer replacement under the pavement.
When: City utility improvements are substantially complete and being tested. Concrete pavement removal is underway. Construction will be complete in the fall of 2024.
ROLLINGWOOD HILLS (Real. Texas. Roads. project*)
What: Residential water, sanitary sewer, and street improvements in the Rollingwood Hills subdivision. Paving improvements will include both concrete reconstruction and asphalt milling and overlay..
When: Paving reconstruction is substantially complete. Some sidewalk sections and ramps remain to be finished. Project is scheduled to be complete this summer.
EASTRIDGE PARK (Real. Texas. Roads. project*)
What: Residential water and street improvements in various areas in and around Eastridge Park neighborhood. Sections of concrete pavement have been identified for removal and replacement along with some sidewalks and alley approaches.
When: Paving reconstruction is substantially complete. Some sidewalk sections and ramps remain to be finished. Project is scheduled to be complete this summer.
WISER ROAD (near Markout Central to near the Holzapfel Pump Station)
What: Project includes asphalt milling and overlay (removal of the existing asphalt pavement to correct, restore, and smooth the surface for resurfacing). Temporary closures may require Markout Central to be used for local access.
When: Project has been bid and will be constructed starting in the summer.
BIG TOWN BOULEVARD (Samuell Boulevard to the City limits)
What: Concrete pavement reconstruction of identified areas including isolated curb and median repairs. Project includes comprehensive asphalt milling and overlay (removal of the existing asphalt pavement to correct, restore, and smooth the surface for resurfacing).
When: Concrete replacement is underway. Expect lane closures in both directions. Project will be complete in July.
SOUTH PARKWAY – U.S. 80 to Peachtree Road (Real. Texas. Roads. project*)
What: Utility and paving reconstruction of a two-lane residential collector street to include areas of on-street parking. Sections of the road will be closed during different phases of construction. Residents will have alley access to their homes.
When: City utilities are underway. South Parkway is now closed to thru traffic except for City services and deliveries.
For information and an interactive map on all current and future City of Mesquite transportation projects, visit www.cityofmesquite.com/PublicWorksProjects.
*Real. Texas. Roads. is the program name for the road repairs funded by the $125 million bond sale approved by voters in November 2015. Repairs under this program are limited to residential, two-lane roadways. Learn more about Real. Texas. Roads.
The Texas Department of Transportation (TxDOT) manages reconstruction and repair for IH-635, IH-30, IH-20, U.S. 80, and the work on Lawson Road under the Highway Safety Improvement Program grant. For TxDOT updates, visit www.drivetexas.org.