Word on the Street Posted on April 02, 2025 | Last Updated on April 02, 2025

FP Lucas construction April 2025F. P. LUCAS BOULEVARD – McKenzie Road to E. Cartwright Road
What
: Existing two-lane asphalt road will be replaced with a new four-lane divided concrete road. The project includes new water and sewer utilities, along with a new multi-use trail and a new bridge section.
When
: Installation of water and sewer utilities are 90% complete, the multi-use trail is 50% complete, and the northbound bridge is 75% complete with new concrete paving. Concrete road construction from McKenzie Road to Cartwright Road started in March and will be ongoing through late Spring 2025. The project is expected to be complete in Fall 2025.


 Oates construction April 2025

OATES OVERLAY (Gus Thomasson to Galloway)
What: New asphalt paving, with sections of sidewalks and curbs repair with new concrete pavement. 
When: Concrete pavement repair for sidewalks and curbs is 100% complete. Asphalt paving and street markings are 100% complete. Traffic cones and signs were removed in March and all lanes are now open. The project completed in March 2025.


 South Parkway construction April 2025

SOUTH PARKWAY – U.S. 80 to Peachtree Road (Real. Texas. Roads. project*)
What: Reconstruction of new water and sewer utilities and new concrete reconstruction of a two-lane residential street. Sections of the road will be closed during different phases of construction. Residents will have alley access to their homes.
When: Installation of water and sewer utilities are 100% complete and the multi-use trail is 50% complete. The new concrete paving is 75% complete, with the northern half from Peachtree to U.S. 80 95% complete with full completion in early April. Concrete paving on the southern half from U.S. 80 to Peachtree started in early March and is 60% complete with completion in April. The project is expected to be fully complete in Summer 2025.


 Lorraine construction April 2025

VARIOUS STREETS – (Real. Texas. Roads. project*)
What: New water and sewer utility reconstruction and new concrete roads and sidewalks for sections of
 Lorraine Lane, Candise Court, Ivy Drive, Mt. Vernon Drive, Fernwood Drive, Monticello Drive, and the Stoney Glen neighborhood. 
When: Construction started on utilities in late February 2025. The first streets to be worked on are Lorraine Lane and Candise Court. The project will gradually move to the rest of the streets. All road projects are expected to be complete by Spring 2026.

 

For information on all current and future City of Mesquite transportation projects, visit www.cityofmesquite.com/CityConstructionProjects.


*Real. Texas. Roads. is the program name for the road repairs funded by the $125 million bond sale approved by voters in November 2015. Repairs under this program are limited to residential, two-lane roadways. Learn more about 
Real. Texas. Roads.


 The Texas Department of Transportation (TxDOT) manages reconstruction and repair for IH-635, IH-30, IH-20, U.S. 80, and the work on Lawson Road under the Highway Safety Improvement Program grant. For TxDOT updates, visit 