- Home
- Government
- Departments
- Public Works
- Engineering
- La Prada Drive Reconstruction Project
La Prada Drive Reconstruction Project
Last Content Update:
Enhancing our community's infrastructure with modern utilities, improved roadways, and safer pedestrian access.
Location
Motley Drive to Pinehurst Lane
Duration
2 Years
Status
Construction Start: March 2026
About the Project
In partnership with Dallas County, the La Prada Drive Reconstruction project will modernize approximately 1.63 miles of roadway from Motley Drive to Pinehurst Lane. Improvements will replace aging pavement and underground utilities while enhancing safety, drainage, and neighborhood character along this major corridor.
Work includes new paving, storm-drain facilities, water and sanitary-sewer line replacements, updated traffic signals, new sidewalks, driveways, and a shared-use trail. Decorative stamped-concrete features and landscaping will create a more attractive and pedestrian-friendly streetscape.
Between Motley Drive and Barnes Bridge Road, the existing four-lane roadway will be reconfigured to two lanes with a continuous center turn lane and on-street parking. This design calms traffic and provides space for wider sidewalks and trees, promoting a safer and more enjoyable experience for drivers, cyclists, and pedestrians.
During construction, temporary lane closures and detours will occur in phases to maintain local access. The City will provide regular updates through message boards, construction notices, and the project webpage. When complete, La Prada Drive will feature upgraded pavement, modern utilities, and a resilient, accessible corridor that benefits residents and visitors alike.
Project Funding
Funding for the La Prada Drive project is provided through a partnership between the City of Mesquite and Dallas County.
Total Estimated Project Cost
$34,000,863.59
Dallas County Contribution
$8,860,000
City of Mesquite Contribution
$25,140,863.59
Project Map
Overview of the construction project area.
Map is for reference purposes only.
Project Renderings
Conceptual images of the finished La Prada Drive project.
Project Updates
Stay informed with the latest progress reports and milestones from the La Prada Drive project.
Road Closure
March 20, 2026
Demolition work to replace underground utilities on La Prada Drive eastbound has begun.
Road Closure
March 19, 2026
Beginning March 2026, eastbound lanes on La Prada Drive between North Galloway Avenue and Pinehurst Lane will be closed to allow for underground utility construction, including water line installation. This phase is anticipated to continue through the end of July 2026, with traffic shifted to a temporary two-way configuration on the westbound lanes while maintaining neighborhood access via North Galloway Avenue.
Construction Phasing
How work will move through the neighborhood.
Utility work will start near Pinehurst Lane and progress southwest toward Motley. As utilities move through each phase, the contractor will return and pave completed sections instead of waiting until all utility work reaches Motley.
- Utilities begin at Pinehurst Lane and advance southwest.
- Paving follows behind utilities in completed areas.
- This means paving will likely start back near Pinehurst Lane while utilities continue further into the neighborhood.
Construction Notices
Street closures and traffic impacts.
Road Closure
La Prada Dr eastbound lanes will close from N Galloway Ave to Pinehurst Ln starting today for utility and paving work, with estimated closure through July 2026. Westbound traffic will shift to two-way, with neighborhood access via N Galloway Ave.
Notice to Residents
A notice of construction was sent to residents affected by current construction and the road closure.
Project Timeline
Track the progress of each construction phase from planning to completion.
Preliminary Project Study Completed
Preliminary study of design
- Design approval
Review Final Design Completed
Final design of utilities, drainage, streets, and sidewalks
- Kimley-Horn contracted to design
- 1st Public Meeting March 2024
- 2nd Public Meeting August 26, 2025
Bid Construction Completed
Advertise for construction bids.
- Competitive open bid awarded by City Council on December 15, 2025 for construction to McMahon Contracting in the amount of $33,930,863.
Utility Infrastructure In Progress
Underground utility installation and upgrades
- Water lines to be installed
- Sewer lines to be installed
Road Construction Upcoming
Road surface preparation, paving, and lane marking
- Surface preparation
- Concrete paving
- Lane striping
Contact & Support
Have questions or concerns about the construction project? Our team is here to help.
Call Center
24/7 emergency construction issues
(972) 288-7711
Project Office & Hours
1515 N. Galloway Ave.
Mesquite, Texas 75149
Mon-Fri: 8 AM - 5 PM
Public Works, Engineering
Project Team
Meet the key personnel managing this construction project.