Real. Texas. Roads.
Watch the Newest Road Warrior Video The Plan: Real. Texas. Roads. is the program name for the road repairs funded by the $125 million bond sale approved by voters in November 2015. Repairs under this program are for residential, 2-lane roadways. The repairs began in 2016. To view the current construction status of streets selected for the program, visit www.cityofmesquite.com/RealTexasRoads.
What's happening now: Concrete repairs are still in progress on, Royal Crest, Northridge, Summit and Viva Drive (Palm to Emerald). Concrete repairs are complete on Cascade and Cresthill and they are awaiting scheduling for mill and rehabilitation. Resurfacing for Royal Crest, Upland, Pebble Creek, Redmill and Green Leaf are complete. Resurfacing is in progress on Sidney, Rockne, Statler and Morgan Drive.
What's next: Resurfacing will continue on Morgan, Statler, Sidney, Rockne and Viva Drive (the section between Town East Boulevard and Palm Drive). Upon completion, resurfacing will begin on Cascade and Cresthill. Concrete repairs are in progress and are close to completion on Summit, Northridge and Royal Crest (between Kearney and Grubb), Upland, Pebble Creek, Redmill and Green Leaf.
The next list of streets planned for concrete repairs include Alta Vista, Buena Vista, Willowbrook, Lee, Larchmont, Northview Place (cul-de-sac) and Mark Drive, (between Baker and Larchmont).
Estimated completion date: The completion of all streets in the Real. Texas. Roads. program is expected to be completed in the fall of 2024, two years ahead of schedule.