Desco and Harvard

Updates:

** This project is complete **

March 24, 2023: The contractor has completed this neighborhood. There may be small minor clean-up items they will continue with until the end of the month.

October 31, 2022: Notice to Proceed was issued on August 15, 2022. Construction is underway.

Project Description:

RealTexasRoads LogoThis page is dedicated to street repairs on Harvard Drive and Desco Drive. Repairs on these streets are funded through the Real. Texas. Roads. program and covers repairs on the following streets:

Location Map - Desco and Harvard

Expected Construction Process - Reconstruction:

Reconstruction is a complete demolition and rebuild of a street. All curb and gutter and sidewalk is also typically replaced. This method requires full design and frequently requires the use of outside design consultants.


Real. Texas. Roads. is the program name for the road repairs funded by the $125 million bond sale approved by voters in November 2015. Repairs under this program are limited to residential, 2-lane roadways. Click here to see information on the entire program of road repairs.