Updates:
** This project is complete **
December 2, 2020: The contractor has completed all proposed construction and staff is working with the contractor to close out the project.
September 15, 2020: The contractor is pouring the other half of the concrete apron at Galloway on both Mimosa and Park. After this concrete work is complete the contractor will begin the asphalt reclamation process simultaneously on all four streets.
August 26, 2020: Staff held a pre-construction meeting with the contractor on August 20, 2020. The contractor will start work the first week of September by doing minor concrete work on Park and Mimosa. The asphalt reclamation is scheduled to start in mid-September.
August 14, 2020: City Council approved award of construction on July 20, 2020. Staff is currently working to finalize paperwork so the contractor can start. Work is scheduled to begin by early September.