Town Ridge, Pecan Bend, Woodlawn, Skyline Neighborhoods

Updates: RealTexasRoads Logo

June 15, 2020: City Council approved award of contract. Staff has begun working to finalize paperwork before construction can begin.

June 12, 2020: The award of the construction contract is on the agenda for the regular City Council meeting scheduled for June 15, 2020. If council approves award of contract, construction is expected to begin in mid July.

Project Description:

This page is dedicated to street repairs in several neighborhoods being repaired through construction contract #2020-049. Repairs in this neighborhood are funded through the Real. Texas. Roads. program and covers repairs on the following streets:


STREET NAME FROM TO
ALLEGHENY PEACHTREE APPALACHIA
APPALACHIA PEACHTREE ALLEGHENY
BITTER ROOT BRIDGER CATSKILL
BLUEFIELD WOODLAWN HERMITAGE
BRIDGER CULDESAC LARAMIE
CAMP DAVID LUCILLE MONTICELLO
CATSKILL PEACHTREE JAMES EDWARDS
CHOCTAW CULDESAC SOUTH PARKWAY
COLBY CHOCTAW CULDESAC
FALLS CHURCH WOODLAWN HERMITAGE
HASTINGS CHOCTAW WICHITA
HERMITAGE SKYLINE SOUTH PARKWAY
JAMES EDWARDS CATSKILL MEADOWBROOK
KENNETH HOPPER PEACHTREE JAMES EDWARDS
LARAMIE PEACHTREE BRIDGER
LUCILLE ALLEY SE OF JEANETTE MONTICELLO
MAHAN CHOCTAW CULDESAC
MEADOWBROOK CULDESAC JAMES EDWARDS
MEADOWCREST MONTICELLO SPRINGBROOK
PORTSMOUTH WOODLAWN HERMITAGE
POTOMAC WOODLAWN HERMITAGE
ROCKY MEADOWBROOK TIMBERVIEW
SHADWELL WOODLAWN HERMITAGE
SPRINGBROOK SYBIL SKYLINE
SYBIL SKYLINE MT VERNON
TIMBERVIEW PEACHTREE CULDESAC
WARM SPRINGS LUCILLE MONTICELLO
WICHITA GOLDEN GROVE FARLEY
WOODLAWN SKYLINE HERMITAGE
YORKTOWN WOODLAWN HERMITAGE

Peachtree Area Map

Peachtree Area Map

South Parkway Area Map

South Parkway Area Map

Streets Inspector Kenneth Towle will be your project inspector and your primary City contact for the duration of the project. This inspector will be in your area daily, and can be reached at 972-216-6282 (office) or 214-232-1253 (cell) or by email at ktowle@cityofmesquite.com.

Expected Construction Process - Full Depth Concrete Repair at Select Locations :

City staff will determine what areas of the street and sidewalk are in moderate to severe condition and the concrete at those locations will be removed and new reinforced concrete will be poured at those locations. This will not replace entire streets, but will rather replace only the moderate to severe locations of pavement failure. The concrete identified for replacement will vary in size and length. After the concrete is removed and replaced, the contractor will grade, place sod and clean up the area disturbed by the construction. 

Real. Texas. Roads. is the program name for the road repairs funded by the $125 million bond sale approved by voters in November 2015. Repairs under this program are limited to residential, 2-lane roadways. Click here to see information on the entire program of road repairs.