Mesquite Heritage Trail, Phase 2

• Scope – Construction of a trail along the south side of Towne Centre Drive from IH 635 to South Mesquite Creek; then south along the west bank of South Mesquite Creek to US 80; then under US 80 to the trailhead just north of AMC theater.
• Current Status – This is a joint City of Mesquite and Dallas County project. The City is managing design and ROW acquisition. The County will manage the bidding and construction phases. The design plans will be slightly updated with some recent changes and the 100% plans will be resubmitted by the end of February. 
• Schedule – Dallas County is expected to start bidding by July 2018. Construction is estimated to begin in Fall of 2018. 
• Project ContactJohn Stanley, P.E. 972-216-6924