Mesquite Heritage Trail, Phase 2

• Scope – Construction of a trail along the south side of Towne Centre Drive from IH 635 to South Mesquite Creek; then south along the west bank of South Mesquite Creek to US 80; then under US 80 to the trailhead just north of AMC theater.
• Current Status – Design plans and are at 95%. This is a Joint City of Mesquite and Dallas County Project. The City is managing design and ROW acquisition. The County will manage the bidding and construction phases.
• Schedule – Construction is estimated to begin in Spring of 2018.
• Project Contact – Matt Holzapfel, P.E., 972-216-6353