SETBACK VERIFICATIONS
FORM BOARD SURVEY
We will now require the submittal of a certified form
board survey plot plan, prepared by a state of Texas licensed
land surveyor instead of the string line placement. The
form board survey, as well as the string line placement,
must be available to the inspector before the Phase I inspection
will be approved.
It is our intention, by expanding your options, to allow
more flexibility in completing your projects, as well as
providing protection both to you and the City of Mesquite,
to insure that the house complies to the required setbacks
within your subdivision. This policy change will take effect
immediately after receiving this policy notice. All form
board survey are to be left in the permit pouch on the
job site for inspector review during the inspection process.
Approved July 22, 2005
Authorized by:
Building Official City of Mesquite
|