Residential Building Information |
Return to Residential Building Information NEW BUILDER INSPECTION PHASE REQUIREMENTS The following inspections are made by the Building Inspection Division of the City of Mesquite in order to provide for the health and safety of the citizens of Mesquite. The required areas of inspection are building, plumbing, mechanical, electrical and energy. It is the responsibility of each person or firm to assure that an inspection request is made when each phase is ready for inspection. The job superintendent is responsible for requesting all inspections. All work must be inspected and approved before proceeding to the next phase. IMPORTANT : Please have all work completed in each phase before requesting an inspection to assure optimum efficiency and promptness. PHASE I
PHASE II
PHASE III
Note: Must call all trades in for separate inspections. Framing will not be made until Plumbing, Mechanical and Electrical have passed. Plumbing, Mechanical & Electrical inspections may be called in at the same time. PHASE IV
PHASE V
PHASE VI
Note: Must call all trades in for separate inspections. Building final will not be made until all other trades have passed inspections. Energy inspections are required per Senate Bill 365. You, the builder of new homes, are required to hire a third-party inspection company to inspect each dwelling Phase IV and Phase V for energy code compliance. Inspections must comply to the MECcheck design submitted with your permit application. Phase IV Energy Insulation Inspection, HVAC duct and the building envelope are required before sheetrock is added. A Phase IV Energy Final Inspection is required at completion of your home. A copy of the approved inspection must be in your permit pouch before final inspection will be approved by the City of Mesquite. INSPECTION REQUEST LINE |