HOMEOWNER INSPECTION PHASE REQUIREMENTS
The following inspections are made by the Building
Inspection Division of the City of Mesquite in order
to provide for the health and safety of the citizens
of Mesquite. The required areas of inspection are building,
plumbing, mechanical, electrical and energy.
It is the responsibility of each person or firm to
assure that an inspection request is made when each
phase is ready for inspection. The job superintendent/owner
is responsible for requesting allinspections.
All work must be inspected and approved before proceeding
to the next phase.
IMPORTANT : Please have all work completed in each phase before requesting an inspection to assure optimum efficiency and promptness.
PHASE I
- Plumbing rough-in of all sanitary waste and water lines
- Sewer lateral connected to service tap
- Gas yard line installation and test
- Property string lines
PHASE II
- Foundation slab
- Electrical under slab
PHASE III
- Structural framing
- Electrical rough-in
- Plumbing top-out, 2 nd floor rough water test, gas test (inside where applicable) and shower pan water test
- Mechanical rough-in
Note: Must call all trades in for separate
inspections. Framing will not be made until Plumbing,
Mechanical and Electrical have passed. Plumbing,
Mechanical & Electrical
inspections may be called in at the same time.
PHASE IV
- Energy pre-sheetrock inspection
- Windows, doors and skylights SHGC and U-factor labels
- Insulation R-values in walls, ceiling cavities and duct work
- Duct work insulation and joint sealant
PHASE V
- Energy final inspection
- Attic insulation per approved design
- HVAC seer rating
- Electrical wall and ceiling openings sealed
PHASE VI
- Building, electrical, plumbing and mechanical finals
Note: Must call all trades in for separate inspections. Building final will not
be made until all other trades have passed inspections. Energy inspections for
homeowner projects will be conducted by the City of Mesquite Building Inspection
Division.
INSPECTION REQUEST LINE
CALL BY 4:00 P.M. FOR NEXT BUSINESS DAY
(972) 329-8505 |