PROJECT DESCRIPTION:
City Council awarded a construction contract to The Fain Group, Inc. on September 20, 2010 in the amount of $1,964,142.60 to rehabilitate the existing deteriorated or damage concrete street and sidewalk pavement, replacement of median pavement with stamped and stained concrete, installation of handicapped ramps, replace of street lighting with new decorative street light, replacement of roadway pavement markings, upgrading of pedestrian handrails and minor water valve replacements. The construction amount award was
Some driveways that appear to be in good condition must be removed and reconstructed to meet the American Disability Act (ADA) Standards for Accessible Design. The commercial driveways will, if practical, be constructed one half at a time so to allow full access to the facility during construction.
Two lanes of traffic in each direction must remain open except during the period when existing concrete is being removed and loaded into trucks or when new concrete is being poured. The contractor is not permitted to perform construction in more than one lane at a time in either direction. In some cases, the concrete pavement repair will be with High Early Strength Concrete to permit the area to be open to traffic at the end of a 24 hours period.
TENTATIVE SCHEDULE:
The construction calendar day for this project is 300. The effective construction start date established by the City was November 1, 2010. The work is scheduled to be completed by the end of August, 2011. Construction rehabilitation is being done simultaneously in both directions. The contractor is currently on schedule. The contractor has scheduled the work as follows:
| Motley-Rustown | Outside Lanes | 11/18/10 | 02/18/11 |
| Rustown-John Glenn | Outside Lanes | 01/03/11 | 02/10/11 |
| Motley-Rustown | Middle Lanes | 03/14/11 | 04/07/11 |
| Rustown-John Glenn | Middle Lanes | 03/02/11 | 04/05/11 |
| John Glenn-Gus Thomasson | Outside Lanes | 01/24/11 | 02/18/11 |
| Motley-Rustown | Inside Lanes | 02/10/11 | 03/11/11 |
| John Glenn-Gus Thomasson | Middle Lanes | 04/11/11 | 05/16/11 |
| Rustown-John Glenn | Inside Lanes | 01/10/11 | 03/01/11 |
| John Glenn-Gus Thomasson | Inside Lanes | 02/15/11 | 04/08/11 |
| Gus Thomasson-635 | Outside Lanes | 04/11/11 | 05/19/11 |
| Gus Thomasson-635 | Middle Lanes | 07/15/11 | 08/05/11 |
| Gus Thomasson-635 | Inside Lanes | 05/20/11 | 07/14/11 |
| 635-E Emporium | Outside Lanes | 04/20/11 | 05/27/11 |
| 635-E Emporium | Middle Lanes | 07/21/11 | 08/18/11 |
| 635-E Emporium | Inside Lanes | 05/30/11 | 08/26/11 |
WORK IN PROGRESS:
STATUS FOR WEEK OF November 28 2011.
CONCRETE STREET, STREET LIGHT REHABILATION (Town East Blvd from E. Emporium to Motley) C.C. # 2010-063
STATUS FOR WEEK OF November 28, 2011
This Project is Substantially Complete. The contractor is currently working on miscellaneous punch list items.
This project is for repair of concrete street paving, modifications of the medians, and sidewalk replacement from E. Emporium Circle to Motley. It also includes installation of new street lights. A Change Order was also approved to construct improvements to the medians and install sidewalks at the intersection of LBJ and Oates and Galloway and Oates.
This will be the final weekly update for this project.
FURTHER INFORMATION OR QUESTIONS:
Jim Palmer, P.E., Project Engineer
Office: 972-216-6351 Cell: 972-977-0280
Email: jjpalmer@cityofmesquite.com
Jon Nisbett, Public Works Inspector
Office: 972-216-6356 Cell: 972-965-9539
Joe Scott, Alternate Public Works Inspector
Office: 972-216-6355 Cell: 972-816-4006
|